@johnbowker.bsky.socialMichael Barnard, TFIE Strategy @michael-barnard.bsky.social
2026-11-15 15:56 UTC
Darlington's first SMR will exceed C$7.7B including shared works and miss Oct 2030, OPG confirms. Unfinished engineering is affecting construction. What does that mean for the C$20.9B four-reactor plan? briefing.tfie.io/p/ontarios-s...
1 picture (not shown on this phone): Illustration pairing the Darlington nuclear construction site with overlapping engineering and construction work, contr…
0 likes, 2 reposts, 0 replies