MEMO: Update on O-Train East Extension Hitachi, a train-control software sub-contractor to East-West Connectors, detected issues with its safety-critical software, that require update and reprogramming. This means that the forecast for Pre-Trial Running to start has shifted from October to November.

1 picture (not shown on this phone)

Quoting @railfans.ca: O-Train Stage 2 East update: We’re hearing from multiple reliable sources that the planned start of pre-trial running in early October may have been pushed back, with activity now expected to begin in November. (1/2)